A3063/26
Checking status...
ADRunway Operations

Work is in progress near the Runway 24 threshold, with personnel and equipment present.

2026-10-26 06:00 - 2028-06-30 15:00
Duration:LONGaggregated 6 months

Period of Applicability

2026-10-26 06:00 - 2028-06-30 15:00

Timeline Visualization

Get instant access to visual timeline analysis and NOTAM scheduling information with Notamify Pro.

7 days free trial, then $24.9/month. Cancel anytime.

Interpretation

Work in progress near the Runway 24 threshold, with personnel and equipment present, Monday through Friday from 0600 to 1500. A supplement will be issued accordingly.

Map Visualization

Loading map data
Please wait...
© OpenStreetMap contributors

Raw NOTAM

A3063/26 NOTAMN
Q) EBBU/QMRHW/IV/BO /A /000/999/4937N00612E005
A) ELLX B) 2610260600 C) 2806301500
D) MON-FRI 0600-1500
E) RWY 24 WIP IN VCY THR24, PRESENCE OF MEN AND EQUIPMENT. SUP WILL
BE ISSUED ACCORDINGLY.