A4275/26
EST
Checking status...
ADRunway Operations

Power line on runway 16 and 19 approaches may be difficult to see in poor weather.

2026-11-03 14:35 - 2027-01-31 22:00
Duration:LONG3 months EST

Period of Applicability

2026-11-03 14:35 - 2027-01-31 22:00

Timeline Visualization

Get instant access to visual timeline analysis and NOTAM scheduling information with Notamify Pro.

7 days free trial, then $24.9/month. Cancel anytime.

Interpretation

A power line on the approaches to runways 16 and 19, below the 2 percent approach slope, is not clearly visible in poor weather conditions.

Map Visualization

Loading map data
Please wait...
© OpenStreetMap contributors

Raw NOTAM

A4275/26 NOTAMR A3031/26
Q) FACA/QMRLT/IV/NBO/A/000/999/3358S01836E005
A) FACT B) 2611031435 C) 2701312200 EST
E) PWR LINE ON RWY 16 AND RWY 19 APCH BLW 2 PERCENT NOT CLEARLY
VISIBLE DRG POOR WX COND.
Was this helpful?