A1388/26
EST
Checking status...
ADTaxiway Operations

Specified DSM taxiways and the P7 run-up pad are closed.

2026-04-01 01:00 - 2026-09-01 22:00
Duration:LONG6 months EST

Period of Applicability

2026-04-01 01:00 - 2026-09-01 22:00

Timeline Visualization

Get instant access to visual timeline analysis and NOTAM scheduling information with Notamify Pro.

7 days free trial, then $24.9/month. Cancel anytime.

Interpretation

At DSM, taxiways R1, P1, P5, P6, and P7; the P7 run-up pad; taxiway P between P7 and the South GA Hangars apron access; and taxiway P between taxiway B and P1 are closed.

Map Visualization

Loading map data
Please wait...
© OpenStreetMap contributors

Raw NOTAM

A1388/26 NOTAMN
Q) KZMP/QMXLC////000/999/4132N09340W005
A) KDSM
B) 2604010100
C) 2609012200 EST
E) DSM TWY R1, P1, P5, P6, P7, P7 RUNUP PAD, TWY P BTN TWY P7 AND
SOUTH GA HANGARS APN ACCESS, TWY P BTN TWY B AND TWY P1 CLSD