B6591/26
EST
Checking status...
ADMPublication Updates

The taxiway T and apron-drain refurbishment working phases are not yet activated.

2026-10-29 00:00 - 2027-01-12 23:59
Duration:3 months EST

Period of Applicability

2026-10-29 00:00 - 2027-01-12 23:59

Timeline Visualization

Get instant access to visual timeline analysis and NOTAM scheduling information with Notamify Pro.

7 days free trial, then $24.9/month. Cancel anytime.

Interpretation

AIP Supplement S61/26 covers refurbishment of taxiway T and apron water drains at Bari/Palese (LIBD) from 29 October 2026 to 1 April 2028; its working phases have not yet been activated.

Map Visualization

Loading map data
Please wait...
© OpenStreetMap contributors

Raw NOTAM

B6591/26 NOTAMN
Q) LIBB/QFAXX/IV/NBO/A /000/999/4108N01646E005
A) LIBD B) 2610290000 C) 2701122359EST
E) SUP S61/26 IN FORCE FROM 29 OCT 2026 TO 01 APR 2028
'BARI/PALESE (LIBD) REFURBISHING WORKS ON TWY T AND ON THE WATER
DRAINS OF THE APRONS'
WORKING PHASES ARE NOT ACTIVATED YET