A5706/26
Checking status...
ADRunway Operations

Napoli/Capodichino runway and selected taxiway works are in phase 1, with runway redesignation and ILS/DME parameter updates.

2026-11-01 00:00 - 2026-12-23 23:59
Duration:2 months

Period of Applicability

2026-11-01 00:00 - 2026-12-23 23:59

Timeline Visualization

Get instant access to visual timeline analysis and NOTAM scheduling information with Notamify Pro.

7 days free trial, then $24.9/month. Cancel anytime.

Interpretation

AIP AIRAC Supplement S60/26 is in force from 1 November to 23 December 2026 for extraordinary runway and selected taxiway maintenance at Napoli/Capodichino, including redesignation of runway 06/24 as 05/23 and updated operational parameters for both ILS/DME systems. Work phase 1 is active; phase 2 has not yet begun.

Map Visualization

Loading map data
Please wait...
© OpenStreetMap contributors

Raw NOTAM

A5706/26 NOTAMN
Q) LIRR/QMRHW/IV/BO /A /000/999/4053N01417E005
A) LIRN B) 2611010000 C) 2612232359
E) AIP AIRAC SUP S60/26 IN FORCE FM 01 NOV 2026 TO 23 DEC 2026
'AD NAPOLI/CAPODICHINO (LIRN): EXTRAORDINARY MAINTENANCE AND
REHABILITATION WORKS ON THE RUNWAY AND SELECTED TAXIWAY, INCLUDING
THE REDESIGNATION OF RWY 06/24 AS RWY 05/23, UPDATED OPERATIONAL
PARAMETERS OF THE 2 ILS/DME SYSTEMS'.
CURRENT STATUS OF WORKING PHASES:
PHASE 1: ACTIVATED
PHASE 2: NOT ACTIVATED YET