Period of Applicability
2026-10-27 16:00 - 2026-12-31 15:59
Timeline Visualization
Get instant access to visual timeline analysis and NOTAM scheduling information with Notamify Pro.
7 days free trial, then $24.9/month. Cancel anytime.
Interpretation
Work is in progress in three areas north of the runway centre lines: 300–1,170 m east of runway 10L threshold and 105–150 m north of runway 10L/28R centre line; 335–1,200 m west of runway 28R threshold and 105–150 m north of runway 10L/28R centre line; and 1,090–2,805 m east of runway 10R threshold and 105–130 m north of runway 10R/28L centre line. No runway closure is stated.